Most project enquiries arrive as "we need radios for a mine, please quote" and then take two weeks of questions to become quotable. Twelve pieces of information turn that into a single round. None of them requires an RF engineer, and eight of them you already have.

SpecificationWhy it changes..What to send..
ItemWhy it changes the quotationWhat to send if you do not have it
Site plan with distancesSets whether direct handheld coverage is plausible at allA satellite screenshot with two points marked and a rough scale
Buildings, floors, underground areasStructure costs more range than distance; drives repeater count and topologyCount of buildings, floors per building, any basement or tunnel
Headcount and peak shiftDrives radio quantity; peak, not total, drives capacityApproximate number on shift at the busiest hour
Roles needing separate groupsDrives talk-group structure and therefore programming scopeList of job functions that must not share a channel
Existing fleet: make, model, bandDecides whether new units can interoperate or must stand alonePhoto of the model label and the battery compartment
Whether you hold the programming fileDecides whether existing units can be merged into the new planAsk your current dealer; if unclear, say so
Frequency licence statusThe band and bandwidth cannot be proposed without itCopy of the assignment, or the fact that none exists yet
Hazardous-area classificationChanges the terminal model and often the accessory setZone classification per area, from your safety documentation
Dispatch, recording, GPS needsAdds console-side items that are not radiosState yes/no per function, even if unsure of the detail
Destination country and termsDrives export documents, duties and delivery timeCountry, city, and whether you want DDP or DAP
Target date and budget rangeDecides whether a proposal is realistic or aspirationalA date, and a range if one is fixed
Drawings or photosRemoves most of the remaining ambiguityAny plan, even hand-drawn, plus site photos

Requirement Gathering

The reason enquiries take several rounds is not that suppliers are slow; it is that the design branches on information the buyer did not know was load-bearing. Distance and structure decide whether a repeater is needed. Peak shift size, not total headcount, decides how many radios are on the floor. The licence decides the band, and the band decides which models are even eligible. Hazardous-area classification can change the handheld model, the battery and the headset, and it is the item most often discovered late, after the price has been agreed. None of this requires technical preparation: eight of the twelve items are facts about your own operation. Send them in one message, even roughly. A rough number that is honestly labelled is far more useful than a precise figure invented to fill a field.

Quotation Inputs

Two rules make the enquiry efficient. First, say which items are missing rather than leaving the field blank, so the supplier knows whether you have no answer or simply did not reach that field. Second, ask for the reasoning in the response, not just the price: why this many radios, why this many repeaters, why this band, and which lines are optional. A proposal that answers those four questions can be reviewed in an afternoon; a price list cannot be reviewed at all, because there is nothing to check it against. If the site is a tender, add the compliance documents you will be judged on - certification evidence per exact model variant, warranty terms, and delivery commitments - to the first message rather than the fifth. Suppliers who cannot supply those quickly are telling you something useful early.

Data Source: Data set mirrors the project requirement form published on /systems and /quote, which was written from the questions that actually change a configuration. No project examples are cited.

Fleet Pricing & Lead Time

Send your model list and quantities — pricing, stock and DAP/DDP terms within one working day.

Get a Quote